Saturday, July 16, 2011

July 7, 2011 - Isolation Pockets and Full Penetration Welding

With the majority of the two steel packages in place and the second floor slab poured, workers are now tending to smaller miscellaneous items.

Now that the second floor slab is placed and the steel columns are true,
the isolation pockets at the base of the East wall columns are being filled with concrete,

Looking south down central corridor in the clinic, sterilization is to the right.
These isolation pockets at the base of the short columns are round and still need to be filled with concrete.

Welder works on full penetration welds as Special Inspector stands by.
Each one of these special Full Penetration Welds takes about half a day.
There are at least 40 of these welds required on the project.

Detail of completed weld.

Special Inspector sign-off of completed weld.
Translation: "Inspected by MT, weld is OK, June 30th"

Welder works off special platform in a hard to reach spot.
Detail of platform.

Workers preparing to pour the slab in the mechanical penthouse.

Tuesday, July 5, 2011

July 5, 2011 - Second Floor Slab

Last Tuesday, June 28th, 2011, the second floor slab was poured.  This is a significant milestone in the project.  Now that the second floor slab is in place, the pace of construction should pick up. 

Concrete placement started at daybreak.
The concrete specifications call for a 5,000 psi mix.    It took several truckloads to complete the pour.
The morning after the pour.
Looking out towards the Eastern curved wall.

Slab edge detail at curved wall.

Looking back at the connector and elevator shaft.

Connector slab and building slab edges.

Monday, June 27, 2011

June 24, 2011 - Second Floor Slab Prep

Second Floor Steel Decking prior to Concrete
Looking South towards the Connector and Elevator Shaft
Penetrations in the slab are mapped out ahead of the pour 
This is a floor drain in the utility room.
That tube connected to the drain is part of the trap primer.
Here is a typical trap primer schematic.
A View out from the top landing of the North Stair

Saturday, June 18, 2011

June 17, 2011 - Scenes from the Second Floor

View looking North along the East wall.
Spandrel Slab detail
Shear Studs welded to the structure below connect the slab to the steel framing.
Those two pieces of Red Iron are for anchoring posts which will frame the rooftop mechanical garden
Future second floor classroom.

Box out in slab for air-conditioning ductwork.
View looking down the corridor to the connector.  Elevator is on the left.
Elevator machine connects through those three conduits.



Thursday, June 16, 2011

June 11, 2011 - Begin Steel Decking and a Few more Views





The second floor slab begins to take shape



Slab edge detail at the East Wall columns

View into the clinic from the Patient entry

Future clinic corridor with sterilization on the right


From this view, the addition appears to be hiding behind the tree.



Saturday, June 4, 2011

June 4, 2011 - Taking Shape

South end of the building

Curve along the Eastern Facade begins to take shape

s
Sculptural portal at south end of Eastern Facade

View from the job trailer