Last week Precision Walls installed the partition framing on the second floor while the plumbers, RC Jacobs, worked roughing-in the plumbing from the ground floor below. |
Looking East from the North Stair, second floor. Faculty offices straight ahead and to the left. |
Shared Ground Floor plumbing stack. Mens room to the right and Womens room to the left. |
Looking South, second floor corridor. Classrooms are to the left and to the right. |
These sleeves fit within the cavity wall for plumbing in this location. |
These sleeves will be relocated into the cavity wall to the right. |
Electrical conduits for a wall panel on left and Roof drain sleeve on the right. |
Contractor is using the largest classroom on second floor for material staging. |
Floor slab and curb poured at Mechanical penthouse. Penthouse roof framing and sheathing is also in place. |
Until the next Post... Lookin' Good! |